[ 单选题 ] 整合管理

You are in the middle of executing a major modification to an existing product when you learn that the resources promised at the
beginning of the project are not available. The BEST thing to do is to_________.
A. show how the resources were originally promised to your project
B. re-plan the project without the resources
C. explain the impact if the promised resources are not made available
D. crash the project
你正在对一个现有产品进行一项重大修改的时候, 得知在项目开始时许诺的资源现在无法获得了, 你最好_________。
  • A、
    A. 表明最初资源是如何被承诺给你的项目的
  • B、
    B. 在没有这个资源的条件下重新计划项目
  • C、
    C. 解释如果资源不可得将会造成的影响
  • D、
    D. 赶工项目